Achievements

All achievements

Achievements Where Budget
Construction of new plant, mechanical installation, piping and tanks Domtar, Windsor, QC $75,000,000
Demolition and reconstruction of the plant section destroyed by fire in 2006 Tafisa, Lac Mégantic, QC $24,000,000
Plant construction, boilers and pipe insulation Domtar, Windsor, QC $15,000,000
Turnkey project, effluents treatment Domtar, Windsor, QC $13,500,000
Insulation of piping and PTA and PTT equipment Interquisa, Montréal, QC $13,400,000
Construction of Danville plant Magnola, Danville, QC $10,000,000
Cogeneration Kruger, Brompton, QC $9,100,000
Mechanical and piping work CLM, Fermont, QC $8,000,000
Structural installation (Mont-Wright) Arcelor Mittal $7,215,000
Mechanical work and structural installation CLM, Fermont, QC $6,600,000
Construction of new plant Tafisa, Lac Mégantic, QC $6,000,000
Piping installation ─ Horizon cogeneration project CNRL, Alberta $6,000,000
Mechanical equipment installation (Lumus Canada) Kruger, Brompton, QC $5,000,000
Turnkey project, effluents treatment E.B. Eddy, Hull, QC $5,000,000
Rolling mill plant, phase 1 Technocell $5,000,000
Dismantling and installation of diffuser Domtar, Windsor, QC $4,700,000
Installation of piping, tanks and equipment Specialty Minerals $4,500,000
Extension of plant, phases 2 and 3 Tafisa, Lac Mégantic $4,000,000
Cogeneration project (International System) Cascade, Kingsey Falls, QC $4,000,000
Installation of piping and equipment for recovery on non-condensable gas A.H. Lundberg, La Tuque, QC $4,000,000
Piping and mechanical installation Tafisa, Lac Mégantic, QC $3,800,000
Cogeneration project ─ SNC Lavallin Domtar, Windsor, QC $3,600,000
Piping, mechanical and boiler installation; plant start-up Magnola, QC $3,500,000
Construction of Mintech plant, phases 1 and 2 Pfizer $3,500,000
Insulation, plant reconstruction Tafisa, Lac Mégantic, QC $3,300,000
Dismantling of old plant Domtar, Windsor, QC $3,000,000
Chlorine dioxyde plant Domtar, Quévillon, QC $3,000,000
Installation of 4 boilers and a lime kiln (Sandwell Simons) Domtar, Windsor, QC $2,600,000
Installation of caissons Autoroute 30, QC $2,400,000
Upgrade of wood yard installations and equipment Domtar, Windsor, QC $2,100,000
Installation of 2 bleaching towers Domtar, Windsor, QC $2,000,000
Piping for chlorine plant Domtar, Quévillon, QC $2,000,000
Insulation of 12 reservoirs (Sandwell Simons) Domtar, Windsor, QC $1,800,000
Piping installation, deinking Kruger, Brompton, QC $1,500,000
Structural, equipment and piping installation Ferco, Burlington Vermont $1,500,000
Structure fabrication and installation (Rolls-Royce project) Alta Ltée $1,300,000
Installation of underground piping Cascade, East-Angus, QC $1,000,000
Dismantling of 2 debarkers and relocation on new site (Raoul Guérette) Cascade, East-Angus, QC $1,000,000
Installation of piping and equipment for recovery on non-condensable gas Domtar Windsor, QC $1,000,000
Screen installation Domtar Windsor, QC $970,000
Fabrication and installation of black liquor tank Domtar Windsor, QC $875,000
Piping and equipment installation McCain Foods, Maine $750,000
Repair of liquor tank Rocktenn $600,000
Chip storing silos (Stone Consolidated Beaupré) Andritz $650,000
Cooling tower Domtar, Windsor, QC $560,000
Insulation of causticizing maintenance shop Smurfit stones $500,000
Installation of 4 scrubbers Andritz, Louisiana $450,000
Water tank installation Nunavut $400,000
Annual plant shutdown Domtar $1,500,000 / year

Boilermaking Work

Achievements Where
New plant construction, mechanical installation, piping work and boilermaking Domtar, Windsor, QC
Plant construction, boiler and piping insulation Domtar, Windsor, QC
Piping, tank and equipment installation Specialty Minerals
Piping, mechanical and boiler installation; plant start-up Magnola, Danville, QC
Installation of 4 boilers and a lime kiln (Sandwell Simons) Domtar, Windsor, QC
Installation of 2 bleaching towers Domtar, Windsor, QC
Fabrication and installation of black liquor tank Domtar, Windsor, QC
Chip storing silos (Stone Consolidated Beaupré) Andritz
Cooling tower Domtar, Windsor, QC
Building of water tank Nunavut

Piping Installation Work

Achievements Where
Construction of new plant; mechanical, piping and boiler installation Domtar, Windsor, QC
Plant construction; piping and boiler insulation Domtar, Windsor, QC
Turnkey project – effluents treatment Domtar, Windsor, QC
Cogeneration Kruger, Brompton, QC
Piping and mechanical work Projet minier, Fermont, QC
Piping installation ─ Horizon cogeneration project (CNRL Alberta) Cascade C.I.P., Alberta
Turnkey project – effluents treatment E.B. Eddy, Hull, QC
Piping, tank and equipment installation Specialty Minerals
Plant extension, phases 2 and 3 Tafisa, Lac Mégantic, QC
Cogeneration project (International System) Cascade, Kingsey Falls, QC
Installation of piping and equipment for recovery on non-condensable gas A.H. Lundberg, La Tuque, QC
Mechanical and piping installation Tafisa, Lac Mégantic, QC
Cogeneration project (SNC Lavallin) Domtar, Windsor, QC
Piping, mechanical and boiler installation; plant start-up Magnola, Danville, QC
Chlorine dioxyde plant Domtar, Quévillon, QC
Chlorine plant piping Domtar, Quévillon, QC
Piping installation; deinking project Kruger, Brompton, QC
Installation of underground piping Cascade, East-Angus, QC
Installation of piping and equipment for recovery on non-condensable gas Domtar Windsor, QC
Piping and equipment installation McCain Foods, Maine

Structural Installation

Achievements Where
Demolition and reconstruction of plant section destroyed by fire in 2006 Tafisa, Lac Mégantic, QC
Construction of Danville plant Magnola, Danville, QC
Structure fabrication and installation Projet minier, Fermont, QC
Construction of new plant Tafisa, Lac Mégantic, QC
Construction of Mintech plant, phases 1 and 2 Pfizer
Installation of caissons Autoroute 30, QC
Structure, equipment and piping installation Ferco, Burlington Vermont
Fabrication and installation structure (Rolls-Royce project) Alta Ltée
Structural installation (Mont-Wright) Arcelor Mittal

Mechanical Equipment Work

Achievements Where
Construction of new plant, mechanical, piping and boiler installation Domtar, Windsor, QC
Demolition and reconstruction of plant section destroyed by fire in 2006 Tafisa, Lac Mégantic, QC
Plant construction, boiler and piping insulation Domtar, Windsor, QC
Turnkey project – effluents treatment Domtar, Windsor, QC
Construction of Danville plant Magnola, Danville, qc
Cogeneration Kruger, Brompton, QC
Mechanical and piping work Projet minier, Fermont, QC
Mechanical equipment installation (Lumus Canada) Kruger, Brompton, QC
Rolling mill plant, phase 1 Technocell
Dismantling and installation of circulator Domtar, Windsor, QC
Piping, tank and equipment installation Specialty Minerals
Mechanical and piping installation Tafisa, Lac Mégantic, QC
Cogeneration project (SNC Lavallin) Domtar, Windsor, QC
Piping, mechanical and boiler installation; plant start-up Magnola, Danville, QC
Construction of Mintech plant, phases 1 and 2 Pfizer
Dismantling of old plant Domtar, Windsor, QC
Chlorine dioxyde plant Domtar, Quévillon, QC
Upgrade of wood yard installations and equipment Domtar, Windsor, QC
Dismantling of 2 debarkers and relocation on new site (Raoul Guérette) Cascade, East-Angus, QC
Screen installation Domtar, Windsor, QC
Piping and equipment installation McCain Foods, Maine
Cooling tower Domtar, Windsor, QC
Installation of 4 scrubbers Andritz, Louisiana

Industrial Insulation Work

Achievements Where
Plant construction, piping and boiler insulation Domtar, Windsor, QC
Piping and PTA and PTT equipment insulation Interquisa, Montréal, QC
Plant extension, phases 2 and 3 Tafisa, Lac Mégantic, QC
Insulation, plant reconstruction Tafisa, Lac Mégantic, QC
Insulation of 12 reservoirs (Sandwell Simons) Domtar, Windsor, QC
Insulation of causticizing maintenance shop Smurfit stones

Plant Shutdown Work

Achievements Where
Paper industries Domtar, Kruger, Cascades, Résolu